EAST WILLIAM STREET PROJECT 

Utility Work for E. William St Complete Streets Project

Utility Work on E. William St Complete Streets Project

Construction Update

Construction on the East William Street Project is underway, with Utility improvements and Complete Streets improvements progressing simultaneously. Utility work began in June 2025 and is anticipated to be completed in March 2026. Complete Streets construction began in November 2025 and will continue through fall 2026.

Repaving of E. William Street between Carson Street and Roop Street is planned for spring 2026, weather permitting. The full project is expected to be completed by fall 2026. All construction activities are weather-dependent and subject to change.

Utility Improvements (Completion: March 2026)

  • Most utility work is complete
  • Remaining milestones include waterline tie-ins and removal of existing powerlines (by NV Energy)
  • Once complete, major traffic and access impacts will lessen until paving operations begin

Complete Streets Improvements (Completion: Fall 2026)

  • Concrete work on the north side is complete
  • South side concrete work will begin after utility activities finish
  • Following concrete work: roadway milling and repaving, striping, landscaping, and finishing elements

Working Hours

Monday–Friday: 7 a.m. – 5:30 p.m.

  • Traffic control may occur outside normal hours
  • Occasional night work and full intersection closures during marathon weekends may occur with advance notice

Traffic Control

Traffic control and access will change throughout the project.  The map below shows the general traffic control for the duration of the project.

Get weekly traffic control updates in the weekly Road Report available:

E. William St. CS Project Temporary Traffic Control Map 

Project Improvements

The project includes a complete corridor transformation of William Street between Carson Street and the I-580 interchange. Improvements include:

• Relocating overhead utilities to underground

• Replacing aging water infrastructure

• Installing storm drain to help prevent roadway flooding

• Removal and replacement of existing sidewalks and driveways

• Installation of new sidewalk for continuous connectivity

• Installation of new dedicated bike lanes

• Construction of a new 10-foot-wide multi-use path to increase corridor safety

• Removal and replacement of roadway asphalt

• Replacing traffic signals

• Installation of new street lighting

• Landscaping to beautify the corridor

CONSTRUCTION UPDATES

Latest Update
Archived Updates

BACKGROUND

Project History
East William Street Neighborhood Improvement District
FAQS
Public Outreach
Meetings
Surveys