EAST WILLIAM STREET PROJECT 

Utility Work for E. William St Complete Streets Project

Utility Work on E. William St Complete Streets Project

Construction on the East William Street Project is underway, with Utility improvements and Complete Streets improvements progressing simultaneously. Overhead utility conversion work began in June 2025 and is anticipated to be completed in June 2026. Complete Streets construction began in November 2025 and will continue through fall 2026.

Repaving of E. William Street between Carson Street and Roop Street is planned for spring 2026, weather permitting. The full project is expected to be completed by fall 2026. All construction activities are weather-dependent and subject to change.

Utility Improvements (Completion: Spring 2026)

  • Most utility work is complete
  • Remaining milestones include waterline tie-ins and removal of existing powerlines (by NV Energy)
  • Once complete, major traffic and access impacts will lessen until paving operations begin

Complete Streets Improvements (Completion: Fall 2026)

  • Concrete work on the north side is complete
  • South side concrete work will begin after utility activities finish
  • Following concrete work: roadway milling and repaving, striping, landscaping, and finishing elements

Working Hours

Monday–Friday: 7 a.m. – 5:30 p.m.

  • Traffic control may occur outside normal hours
  • Occasional night work may occur
  • Marathon weekend work is possible during paving.  Advance notice will be provided to the community.

Traffic Control: June 27 – July 10, 2026

Paving on East William Street between Carson Street and Roop Street begins Saturday, June 20. Operations are expected to continue through Friday, July 10.

Drivers can expect the following traffic patterns and road closures:

June 27-July 2

  • William Street will be fully closed to both eastbound and westbound traffic between Carson Street and Roop Street.
  • All connecting northbound and southbound side streets will be closed.
  • Carson Street and Roop Street intersections will remain open.

Williams St TC June 27 - July 2

July 6-10

  • The Carson Street/William Street intersection will be fully closed to traffic (Mon-Fri).
  • The Roop Street/William Street intersection will be fully closed to traffic (Tue-Fri).
  • Williams Street remains closed between the Carson and Roop intersections.
  • The Stewart Street/William Street intersection remains open to northbound and southbound traffic.
  • Mills Park remains open and accessible from William Street.

 William Street Traffic Control Plan Week of July 6

No construction work will occur during the Independence Day holiday.

Motorists are encouraged to plan ahead, allow extra travel time, and follow all posted traffic control signage. Access to businesses and residences will be maintained.

Get weekly traffic control updates in the weekly Road Report available:

Project Improvements

The project includes a complete corridor transformation of William Street between Carson Street and the I-580 interchange. Improvements include:

  •  Relocating overhead utilities to underground
  •  Replacing aging water infrastructure
  •  Installing storm drain to help prevent roadway flooding
  •  Removal and replacement of existing sidewalks and driveways
  •  Installation of new sidewalk for continuous connectivity
  •  Installation of new dedicated bike lanes
  •  Construction of a new 10-foot-wide multi-use path to increase corridor safety
  •  Removal and replacement of roadway asphalt
  •  Removing one eastbound lane near the Carson Street intersection to help calm traffic and increase safety for all users in the downtown corridor.
  •  Replacing traffic signals
  •  Installation of new street lighting
  •  Landscaping to beautify the corridor

CONSTRUCTION UPDATES

Latest Update
Archived Updates

BACKGROUND

Project History
East William Street Neighborhood Improvement District
FAQS
Public Outreach
Meetings
Surveys