UPDATE – 03/03/2026
Construction continues along E. William Street. Utility improvements between Carson St. and Roop St. are nearing completion. Remaining utility work includes waterline tie-ins and removal of existing powerlines. Concrete work on the north side is complete, and concrete on the south side will begin once utility work finishes. Roadway milling and repaving are planned for spring 2026, followed by striping, landscaping, and final improvements, with full project completion anticipated in fall 2026. Utility work east of Roop St. will continue over the upcoming months as progress is made towards the east end of the project. Concrete work east of Roop St. will follow completion of the utility work.
UPDATE – 12/03/2025
Construction continues along E. Williams St., primarily between Carson St. and Roop St. (Zone 1). Replacement of sidewalk, driveways, and other surface improvements is underway and the majority of the underground utility work is complete. Underground utility work between Roop and Saliman (Zone 2) will begin this month.
UPDATE – 10/20/2025
**William St./Carson St. Intersection Closures October 20th through 30th**
As part of the William Street Project, crews will be completing major underground utility improvements in the intersection of Carson and William Street from October 20th through October 30th. Please plan ahead for delays and detours in this area. Work will include new sewer and water line installation as well as traffic signal underground infrastructure. Thank you for your patience as we make these important improvements!
🔹 Week of October 20
➡️ Full closure Mon–Fri, 6am–6pm for new waterline installation.
➡️ During non-working hours, one lane in each direction (North/South) will reopen.
➡️ East/West travel will remain closed 24 hours a day.
🔹 Week of October 27
➡️ Full closure begins Sun evening, Oct. 26 at 6pm, continuing 24 hours/day through Thurs afternoon (Oct. 30).
UPDATE – 9/23/2025
Underground Utility Installation Continues and Storm Drainage Improvements Begin
Construction crews are mostly complete with the underground infrastructure that will house the overhead power and communication lines. Next up will be coordinating with Nevada Energy, ATT, and Charter to populate the underground conduit and work on re-supplying service to adjacent properties through the newly installed improvements. Construction of the storm drainage improvements is also underway. Inlets are being added between Carson and Roop so that water no longer needs to run a long distance in the curb before entering the underground storm drainage system. Water and sewer system improvements will be underway soon!
UPDATE – 8/26/2025
Underground Utility Installation Progresses on William Street
Construction crews are currently installing underground conduit to relocate overhead power and communication lines along William Street. The contractor has completed the primary conduit run from Carson to Roop Street and is now extending the system toward Saliman Street. These conduits will accommodate NV Energy power lines as well as Charter and AT&T communication infrastructure.
This undergrounding initiative represents a key step in modernizing the William Street corridor and advancing the city's vision of creating an integrated Complete Streets network. The utility relocation phase is scheduled for completion by mid-October 2025, with Complete Streets improvements beginning concurrently in early September.
UPDATE – 5/29/2025
Construction activities for the East William Street Project are scheduled to begin June, 2025. Carson City will host a pre-construction public meeting regarding construction schedule and activities for the project on Tuesday, June 3rd, 2025 for the public to meet with City staff and ask questions regarding the project. The meeting will be held at 5:30 p.m. in the Bonanza Room at the Carson City Community Center located at 851 E William St, Carson City, NV 89701.
During the public meeting, Carson City Public Works will present information on the following:
- Project Background and Overview
- Construction Process and Schedule
- How to Stay Informed as the Project Progresses
A PDF of the pre-construction public meeting presentation slides will be posted to this website after the meeting.
UPDATE - Feb 12, 2025
The East William Street Complete Street Project will be advertised for contractor bids February-March of 2025. Once bids are received, the City will review and award the construction contract. The City is fortunate to receive federal funding for the project and with the funding comes additional steps for advertising, reviewing, and awarding the construction contract. The following is the latest schedule for what to expect in the coming months:
February – March: Project advertised for contractor bids
March – April: Receive bids, review, and submit for approval to award
April – May: Award construction contract
June: Hold pre-construction public meeting
Summer 2025: Begin construction!
Additional information will be provided on the construction public meeting and schedule as it is available.